Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Jaunpur
AGENCY AFCONS
SCHEME ID 20066708
SCHEME NAME MARHAT VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST 343.77
EXPENDITURE 193.31
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 16159.00 Meter
Length Laid 14547.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Jaunpur Khuthan Marhat 468627 Marhat 157 157 100% Har Ghar Jal Not Certified
2 Jaunpur Khuthan Marhat 468628 Chakbarna 35 27 77% Work In Progress Not Certified
3 Jaunpur Khuthan Mohammadpur 468635 Baharipur 98 78 80% Work In Progress Not Certified
4 Jaunpur Khuthan Mohammadpur 468638 Mohammadpur 116 97 84% Work In Progress Not Certified