Scheme Details
DISTRICT
Azamgarh
AGENCY
GA INFRA - BABA (JV)
SCHEME ID
20066710
SCHEME NAME
Karmaini water supply scheme
ESTIMATED COST
472.22
EXPENDITURE
367.83
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
25887.00
Meter
Length Laid
24987.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Haraiya | Karmaini | 461935 | Karmaini | 685 | 673 | 98% | Work In Progress | Not Certified |