Scheme Details
DISTRICT
Etawah
AGENCY
OMIL-JWIL (JV)
SCHEME ID
20066725
SCHEME NAME
CHOBIYA W/S SCHEME PWS
ESTIMATED COST
330.65
EXPENDITURE
167.41
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
21462.00
Meter
Length Laid
20750.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Basrehar | Chobiya | 419757 | Chobiya | 497 | 494 | 99% | Work In Progress | Not Certified |
| 2 | Etawah | Basrehar | Chobiya | 419758 | Jain Pur Chobiya | 86 | 80 | 93% | Work In Progress | Not Certified |