Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Welspun Kaveri Infraprojects JV | 20066784 | Gabhiran | 427.34 | 79.83 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 22701.00 | 22000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Khuthan | Nooruddinpur | 468614 | Jainpur | 43 | 38 | 88 | Work In Progress | Not Certified |
| 2 | Jaunpur | Khuthan | Nooruddinpur | 468615 | Nooruddinpur | 80 | 34 | 42 | Work In Progress | Not Certified |
| 3 | Jaunpur | Khuthan | Nooruddinpur | 468616 | Methenepur | 42 | 32 | 76 | Work In Progress | Not Certified |
| 4 | Jaunpur | Khuthan | Ranipur | 468653 | Ranipur | 137 | 137 | 100 | Har Gar Jal | Not Certified |
| 5 | Jaunpur | Khuthan | Ranipur | 468654 | Zalibpur | 93 | 93 | 100 | Har Gar Jal | Not Certified |
| 6 | Jaunpur | Khuthan | Gabhiran | 468657 | Gabhiran | 251 | 180 | 72 | Work In Progress | Not Certified |