Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | UNIVERSAL MEP | 20066798 | BHAVANIGARH & HASAI MUKUNDPUR GRAM PANCHYAT WATER SUPPLY SCHEME | 331.61 | 222.87 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 15007.00 | 15007.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Waldirai | Hasui Mukundpur | 439378 | Hasui Mukundpur | 226 | 226 | 100 | Har Gar Jal | Certified |
| 2 | Sultanpur | Waldirai | Bhawani Garh | 439379 | Bhawani Garh | 200 | 200 | 100 | Har Gar Jal | Certified |