Scheme Details
DISTRICT
Sultanpur
AGENCY
UNIVERSAL MEP
SCHEME ID
20066821
SCHEME NAME
BAROLI & PALI GRAM PANCHYAT WATER SUPPLY SCHEME
ESTIMATED COST
422.84
EXPENDITURE
323.37
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
25645.00
Meter
Length Laid
25546.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Dhanpatganj | Barouli | 440022 | Barouli | 155 | 153 | 99% | Work In Progress | Not Certified |
| 2 | Sultanpur | Dhanpatganj | Barouli | 440023 | Bhagvanpur | 63 | 60 | 95% | Work In Progress | Not Certified |
| 3 | Sultanpur | Dhanpatganj | Barouli | 440024 | Dikhoura | 73 | 70 | 96% | Work In Progress | Not Certified |
| 4 | Sultanpur | Dhanpatganj | Pali | 440048 | Pali | 286 | 282 | 99% | Work In Progress | Not Certified |