Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | NCC Ltd. | 20066887 | Jagdishpur Urf Pandeypur JJM | 176.78 | 171.30 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 13 | 13 | Yes | 0 | NA | No | 8997.00 | 11656.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Uruwa | Jagdishpur Urf Pandeypur | 455907 | Jagdishpur Urf Pandeypur | 111 | 111 | 100 | Har Gar Jal | Certified |
| 2 | Gorakhpur | Uruwa | Jagdishpur Urf Pandeypur | 455908 | Sarsaikast Har Prasad | 104 | 104 | 100 | Har Gar Jal | Certified |