Scheme Details
DISTRICT
Kaushambi
AGENCY
GA INFRA - BABA (JV)
SCHEME ID
20066894
SCHEME NAME
Jafarpur Mahauwa Water Supply Scheme
ESTIMATED COST
394.98
EXPENDITURE
135.80
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
10
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10635.00
Meter
Length Laid
12802.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | Sarsawan | Jafarpur Mahauwa | 431148 | Jafarpur Mahauwa | 898 | 895 | 100% | Work In Progress | Not Certified |