| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | NCC Ltd. | 20066971 | JADWAPUR JJM | 231.67 | 185.81 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 16 | Yes | 0 | NA | No | 18909.00 | 13603.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Belghat | Jadwapur | 456928 | Yadwapur | 74 | 74 | 100 | Har Gar Jal | Certified |
| 2 | Gorakhpur | Belghat | Jadwapur | 456929 | Ranjitgarh | 71 | 71 | 100 | Har Gar Jal | Certified |
| 3 | Gorakhpur | Belghat | Jadwapur | 456930 | Jhae | 75 | 75 | 100 | Har Gar Jal | Certified |
| 4 | Gorakhpur | Belghat | Jadwapur | 456931 | Purwa | 45 | 45 | 100 | Har Gar Jal | Certified |
| 5 | Gorakhpur | Belghat | Jadwapur | 456932 | Dugdhkunda | 7 | 7 | 100 | Har Gar Jal | Certified |
| 6 | Gorakhpur | Belghat | Jadwapur | 456933 | Gosaepur | 11 | 11 | 100 | Har Gar Jal | Certified |