Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | NCC Ltd. | 20067002 | Chak Saraya JJM | 195.05 | 179.73 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 16 | Yes | 0 | NA | No | 7721.00 | 7828.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Uruwa | Chak Saraya | 456051 | Chak Saraya | 178 | 178 | 100 | Har Gar Jal | Certified | 
| 2 | Gorakhpur | Uruwa | Chak Saraya | 456052 | Mathjairam | 21 | 21 | 100 | Har Gar Jal | Certified | 
| 3 | Gorakhpur | Uruwa | Chak Saraya | 456053 | Khorara | 27 | 27 | 100 | Har Gar Jal | Certified | 
| 4 | Gorakhpur | Uruwa | Chak Saraya | 456054 | Dumari | 25 | 25 | 100 | Har Gar Jal | Certified |