Scheme Details
DISTRICT
Budaun
AGENCY
PNC-SPML-JV
SCHEME ID
20067120
SCHEME NAME
MUGARRA &SARELI PUKHTA WATER SUPPLY SCHEME
ESTIMATED COST
380.11
EXPENDITURE
92.05
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11998.00
Meter
Length Laid
11998.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Usawan | Sareli Pukhta | 402528 | Sareli Pukhta | 384 | 383 | 100% | Work In Progress | Not Certified |
| 2 | Budaun | Usawan | Mugrra | 402529 | Mugarra | 104 | 103 | 99% | Work In Progress | Not Certified |
| 3 | Budaun | Usawan | Mugrra | 402533 | Mirzapur Basant | 78 | 77 | 99% | Work In Progress | Not Certified |