Scheme Details
DISTRICT
Budaun
AGENCY
PNC-SPML-JV
SCHEME ID
20067127
SCHEME NAME
BHAKROLI & KHIRIA MADHUKAR PUKHTA WATER SUPPLY SCHEM
ESTIMATED COST
317.57
EXPENDITURE
118.72
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10322.00
Meter
Length Laid
10322.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Usawan | Bhakroli | 402526 | Bhakroli | 218 | 218 | 100% | Har Ghar Jal | Not Certified |
| 2 | Budaun | Usawan | Khiria Madhukar Pukhta | 402527 | Khiria Madhukar Pukhta | 428 | 428 | 100% | Har Ghar Jal | Not Certified |