Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Budaun
AGENCY PNC-SPML-JV
SCHEME ID 20067133
SCHEME NAME KUNWAR GAUN & SHAHPUR WATER SUPPLY SCHEME
ESTIMATED COST 438.97
EXPENDITURE 154.41
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 37
Procured 37 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 15740.00 Meter
Length Laid 15740.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Budaun Usawan Kunwar Gaun 402562 Kunwar Gaun 596 596 100% Har Ghar Jal Not Certified
2 Budaun Usawan Shahpur 402564 Shahpur 258 258 100% Har Ghar Jal Not Certified