Scheme Details
DISTRICT
Pilibhit
AGENCY
VISHVARAJ
SCHEME ID
20067195
SCHEME NAME
SISAIYA Gram Panchayat Water Supply Scheme
ESTIMATED COST
139.91
EXPENDITURE
119.70
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
13
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
4568.00
Meter
Length Laid
4568.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Marori | Sisaiya | 404754 | Sisaiya | 318 | 318 | 100% | Har Ghar Jal | Certified |