Scheme Details
DISTRICT
Bijnor
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20067227
SCHEME NAME
Talibpur water supply scheme
ESTIMATED COST
271.68
EXPENDITURE
222.25
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
22
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12090.00
Meter
Length Laid
11032.20
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Jalilpur | Talibpur | 387459 | Talibpur | 182 | 182 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bijnor | Jalilpur | Talibpur | 387460 | Mirzapur Bakaina | 99 | 99 | 100% | Har Ghar Jal | Not Certified |
| 3 | Bijnor | Jalilpur | Talibpur | 387461 | Bakaina | 129 | 129 | 100% | Har Ghar Jal | Not Certified |