Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Budaun
AGENCY PNC-SPML-JV
SCHEME ID 20067312
SCHEME NAME TALIBNAGAR &MAKRANDPUR WATER SUPPLY SCHEME
ESTIMATED COST 288.64
EXPENDITURE 151.48
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 9479.00 Meter
Length Laid 9479.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Budaun Wazirganj Makrandpur 401422 Makrandpur 250 250 100% Har Ghar Jal Not Certified
2 Budaun Wazirganj Talibnagar 401423 Talibnagar 91 91 100% Har Ghar Jal Certified
3 Budaun Wazirganj Talibnagar 401424 Lakhupura 74 74 100% Har Ghar Jal Certified