Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Budaun
AGENCY PNC-SPML-JV
SCHEME ID 20067328
SCHEME NAME PARISIDDHIPUR & DUDHARI WATER SUPPLY SCHEME
ESTIMATED COST 364.16
EXPENDITURE 161.48
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 27
Procured 27 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 11772.00 Meter
Length Laid 11772.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Budaun Dataganj Parisiddhpur 402311 Parisiddhpur 253 251 99% Work In Progress Not Certified
2 Budaun Dataganj Dudhari 402312 Dudhari 300 299 100% Work In Progress Not Certified
3 Budaun Dataganj Dudhari 402313 Hashimpur 143 142 99% Work In Progress Not Certified