Scheme Details
DISTRICT
Raebareli
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20067425
SCHEME NAME
GAUHANNA WATER SUPPLY SCHEME
ESTIMATED COST
179.01
EXPENDITURE
94.58
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
4010.00
Meter
Length Laid
3520.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Amawan | Gauhanna | 416685 | Gauhanna | 206 | 137 | 67% | Work In Progress | Not Certified |