Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Bijnor Vindhya-GAJA (JV) 20067431 Sultanpur Abad water supply scheme 203.77 140.24 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 0 16 16 Yes 0 NA No 7135.00 7258.80

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Bijnor Haldaur Sultanpur Abad 386286 Sultanpur Abad 191 173 91 Work In Progress Not Certified
2 Bijnor Haldaur Sultanpur Abad 386287 Rustampur Bajid 101 86 85 Work In Progress Not Certified