Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Ambedkar Nagar
AGENCY Vindhya-GAJA (JV)
SCHEME ID 20067432
SCHEME NAME BARAGAON Water Supply Scheme
ESTIMATED COST 572.93
EXPENDITURE 515.31
AUTOMATION STATUS
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 5
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 37
Procured 38 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 37422.00 Meter
Length Laid 38933.90 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

5 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Ambedkar Nagar Jahangirganj RAIPUR BELWA DANDI 438193 RAMPUR BELWADANDI 280 274 98% Work In Progress Not Certified
2 Ambedkar Nagar Jahangirganj Baragaon 438194 Baragaon 237 230 97% Work In Progress Not Certified
3 Ambedkar Nagar Jahangirganj KINNUPUR 438195 JOGIPUR 131 127 97% Work In Progress Not Certified
4 Ambedkar Nagar Jahangirganj KINNUPUR 438196 DHANIKPUR 51 51 100% Har Ghar Jal Not Certified
5 Ambedkar Nagar Jahangirganj KINNUPUR 438197 KINNUPUR 172 160 93% Work In Progress Not Certified