Scheme Details
DISTRICT
Saharanpur
AGENCY
Gayatri Projects LTD
SCHEME ID
20067617
SCHEME NAME
JADAUDA JATT
ESTIMATED COST
412.35
EXPENDITURE
0.00
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
28
Procured
0
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10723.00
Meter
Length Laid
10300.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Deoband | JADAUDA JATT | 384594 | Jaratha Jatt | 852 | 851 | 100% | Work In Progress | Not Certified |
| 2 | Saharanpur | Deoband | JADAUDA JATT | 384595 | Salempur | 40 | 40 | 100% | Har Ghar Jal | Not Certified |
| 3 | Saharanpur | Deoband | JADAUDA JATT | 384596 | Nihal Kheri | 153 | 152 | 99% | Work In Progress | Not Certified |