Scheme Details
DISTRICT
Sitapur
AGENCY
NCC Ltd.
SCHEME ID
20067708
SCHEME NAME
Mahmudpur Rohila & Pipri Kalan Water Supply SCheme
ESTIMATED COST
375.54
EXPENDITURE
133.61
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
28
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11408.00
Meter
Length Laid
11000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Ealliya | Mahmudpur Rohila | 410236 | Jamduwa | 129 | 128 | 99% | Work In Progress | Not Certified |
| 2 | Sitapur | Ealliya | Mahmudpur Rohila | 410237 | Mahmudpur | 136 | 136 | 100% | Har Ghar Jal | Not Certified |
| 3 | Sitapur | Ealliya | Mahmudpur Rohila | 410238 | Rohila | 105 | 103 | 98% | Work In Progress | Not Certified |
| 4 | Sitapur | Ealliya | Pipri Kalan | 410269 | Muradpur | 41 | 40 | 98% | Work In Progress | Not Certified |
| 5 | Sitapur | Ealliya | Pipri Kalan | 410270 | Pipri Kalan | 195 | 182 | 93% | Work In Progress | Not Certified |