Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Jaunpur
AGENCY Welspun Kaveri Infraprojects JV
SCHEME ID 20067745
SCHEME NAME Chilbili
ESTIMATED COST 355.18
EXPENDITURE 142.20
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 27
Procured 27 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 19119.00 Meter
Length Laid 13500.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Jaunpur Suithkala Chilbili 468192 Chilbili 237 226 95% Work In Progress Not Certified
2 Jaunpur Suithkala Chilbili 468193 Barauna 130 118 91% Work In Progress Not Certified
3 Jaunpur Suithkala Chilbili 468194 Benipur Sarahara 107 52 49% Work In Progress Not Certified