Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20067806 | MACHHALIGAON & BANGAON PATTI Village Village water supply scheme | 759.99 | 211.54 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 75409.00 | 21098.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Badlapur | Bangaon Patti | 468816 | Bangaon Patti | 225 | 123 | 55 | Work In Progress | Not Certified | 
| 2 | Jaunpur | Badlapur | Machhaligaon | 468855 | Newada Mureedpur | 146 | 102 | 70 | Work In Progress | Not Certified | 
| 3 | Jaunpur | Badlapur | Machhaligaon | 468856 | Machhaligaon | 522 | 429 | 82 | Work In Progress | Not Certified |