Scheme Details
DISTRICT
Saharanpur
AGENCY
GA INFRA - BABA (JV)
SCHEME ID
20067810
SCHEME NAME
BILASHPUR
ESTIMATED COST
231.49
EXPENDITURE
129.40
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7446.00
Meter
Length Laid
6446.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Nagal | Bilaspur | 636079 | Bilaspur | 409 | 409 | 100% | Har Ghar Jal | Not Certified |