Scheme Details
DISTRICT
Bijnor
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20067858
SCHEME NAME
SALEMPUR WATER SUPPLY SCHEMS
ESTIMATED COST
385.34
EXPENDITURE
314.48
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
22
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
25638.00
Meter
Length Laid
24923.12
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Jalilpur | SALEMPUR | 387336 | Salempur | 354 | 344 | 97% | Work In Progress | Not Certified |
| 2 | Bijnor | Jalilpur | SALEMPUR | 387337 | Baliyanangali | 47 | 18 | 38% | Work In Progress | Not Certified |
| 3 | Bijnor | Jalilpur | SALEMPUR | 387338 | Mirapur Sikri Ahatmali | 5 | 1 | 20% | Work In Progress | Not Certified |
| 4 | Bijnor | Jalilpur | SALEMPUR | 655742 | MIRAPUR SIKRI BILA AHATMALI | 23 | 23 | 100% | Har Ghar Jal | Not Certified |