Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20067932 | DHANOR WATER SUPPLY SCHEME | 364.67 | 226.31 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 23 | 23 | Yes | 0 | NA | No | 17873.00 | 17214.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Haldaur | Dhanori | 386186 | Dhanori | 173 | 173 | 100 | Har Gar Jal | Not Certified | 
| 2 | Bijnor | Haldaur | Dhanori | 386187 | Tarikampur Hafiz | 105 | 87 | 83 | Work In Progress | Not Certified | 
| 3 | Bijnor | Haldaur | Dhanori | 386188 | Islampur Chamra | 16 | 8 | 50 | Work In Progress | Not Certified | 
| 4 | Bijnor | Haldaur | Kherki Tappa Nagala | 386198 | Kherki Tappa Nangla | 203 | 176 | 87 | Work In Progress | Not Certified | 
| 5 | Bijnor | Haldaur | Kherki Tappa Nagala | 386199 | Faridpur Malhu | 24 | 5 | 21 | Work In Progress | Not Certified |