Scheme Details
DISTRICT
Budaun
AGENCY
PNC-SPML-JV
SCHEME ID
20068002
SCHEME NAME
Bhau nagla water supply scheme
ESTIMATED COST
205.46
EXPENDITURE
79.13
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
4670.00
Meter
Length Laid
4670.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Mion | Bhau Nagla | 402404 | Bhau Nagla Pukhta | 250 | 245 | 98% | Work In Progress | Not Certified |
| 2 | Budaun | Mion | Bhau Nagla | 402405 | KESHAUNPUR KHURD | 101 | 98 | 97% | Work In Progress | Not Certified |