Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Budaun | PNC-SPML-JV | 20068024 | Sainjania water supply scheme | 238.02 | 81.39 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 16 | Yes | 0 | NA | No | 7083.00 | 7083.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Samrer | Sainjania | 402222 | Sainjania | 179 | 175 | 98 | Work In Progress | Not Certified | 
| 2 | Budaun | Samrer | Sainjania | 402223 | Bauthra | 58 | 55 | 95 | Work In Progress | Not Certified | 
| 3 | Budaun | Samrer | Sainjania | 402224 | Pareva | 83 | 80 | 96 | Work In Progress | Not Certified |