Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | GA INFRA - BABA (JV) | 20068099 | Noorpur Urf Bharooad | 255.16 | 146.53 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 37 | 37 | Yes | 0 | NA | No | 5760.00 | 4000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Sadhauli Kadeem | NOORPUR URF BHARAOOAD | 383417 | NOORPUR URF BHARAOOA | 155 | 154 | 99 | Work In Progress | Not Certified |
| 2 | Saharanpur | Sadhauli Kadeem | NOORPUR URF BHARAOOAD | 383419 | HUSAINPUR | 144 | 133 | 92 | Work In Progress | Not Certified |
| 3 | Saharanpur | Sadhauli Kadeem | NOORPUR URF BHARAOOAD | 694256 | HUSAINPUR | 9 | 0 | 0 | Work In Progress | Not Certified |