Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Jaunpur
AGENCY AFCONS
SCHEME ID 20068180
SCHEME NAME Pahadpur Village water supply scheme
ESTIMATED COST 399.17
EXPENDITURE 197.52
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 26494.00 Meter
Length Laid 24578.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Jaunpur Machhlishahr Paharpur 469525 Paharpur 155 145 94% Work In Progress Not Certified
2 Jaunpur Machhlishahr Paharpur 469526 Jalalabad 69 58 84% Work In Progress Not Certified
3 Jaunpur Machhlishahr Paharpur 469527 Mirzapur 71 62 87% Work In Progress Not Certified
4 Jaunpur Machhlishahr Paharpur 469528 Nikamuddinpur 129 123 95% Work In Progress Not Certified