Scheme Details
DISTRICT
Sitapur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20068188
SCHEME NAME
Basantapur & Rohiya Shivpur Water Supply Scheme
ESTIMATED COST
492.36
EXPENDITURE
282.31
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
28
Procured
28
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
28816.00
Meter
Length Laid
28816.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Behta | Basantapur | 410738 | Bamaula | 120 | 117 | 98% | Work In Progress | Not Certified |
| 2 | Sitapur | Behta | Basantapur | 410739 | Basantpur | 301 | 296 | 98% | Work In Progress | Not Certified |
| 3 | Sitapur | Behta | Rohiya Shivpur | 410829 | Raipur | 31 | 1 | 3% | Work In Progress | Not Certified |
| 4 | Sitapur | Behta | Rohiya Shivpur | 410830 | Rohiya Shivpur | 376 | 335 | 89% | Work In Progress | Not Certified |