Scheme Details
DISTRICT
Fatehpur
AGENCY
Power Mech Projects Ltd
SCHEME ID
20068199
SCHEME NAME
CHAK ETAILI
ESTIMATED COST
206.82
EXPENDITURE
82.18
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
18
Procured
18
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6606.00
Meter
Length Laid
6380.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Bahua | Chak Etaili | 428061 | Chak Etaili | 225 | 225 | 100% | Har Ghar Jal | Not Certified |
| 2 | Fatehpur | Bahua | Chak Etaili | 428062 | Chak Chhavinathpur | 83 | 83 | 100% | Har Ghar Jal | Not Certified |
| 3 | Fatehpur | Bahua | Chak Etaili | 428063 | Nartauli | 65 | 65 | 100% | Har Ghar Jal | Not Certified |