Scheme Details
DISTRICT
Hardoi
AGENCY
NCC Ltd.
SCHEME ID
20068248
SCHEME NAME
PEERPUR GOGP JJM
ESTIMATED COST
410.64
EXPENDITURE
287.46
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
28
Procured
28
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14440.00
Meter
Length Laid
13391.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Pihani | Peerpur | 412128 | Peerpur | 200 | 200 | 100% | Har Ghar Jal | Certified |
| 2 | Hardoi | Pihani | Salempur | 412175 | Salempur | 140 | 140 | 100% | Har Ghar Jal | Not Certified |
| 3 | Hardoi | Pihani | SIDAURIYA | 412176 | SIDAURIYA | 100 | 100 | 100% | Har Ghar Jal | Not Certified |
| 4 | Hardoi | Pihani | Salempur | 412177 | PAHADPUR | 30 | 30 | 100% | Har Ghar Jal | Not Certified |
| 5 | Hardoi | Pihani | Salempur | 412178 | HAJIPUR | 90 | 90 | 100% | Har Ghar Jal | Not Certified |