Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | NCC Ltd. | 20068339 | Malikapur & Rampur Bhuda Water Supply Scheme | 479.49 | 217.20 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 35 | 35 | Yes | 0 | NA | No | 21640.00 | 20100.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Ealliya | Malikapur | 410239 | Malikapur | 258 | 254 | 98 | Work In Progress | Not Certified | 
| 2 | Sitapur | Ealliya | Malikapur | 410240 | Sujavalpur | 83 | 77 | 93 | Work In Progress | Not Certified | 
| 3 | Sitapur | Ealliya | Malikapur | 410241 | Udhawapur | 66 | 60 | 91 | Work In Progress | Not Certified | 
| 4 | Sitapur | Ealliya | Rampur Bhuda | 410275 | Rampur Bhuda | 301 | 286 | 95 | Work In Progress | Not Certified |