Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20068345 | CHANDRAMPUR PANSALA GOGP JJM | 775.85 | 355.44 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 2 | 2 | 2 | 2 | 2 | 1 | 1 | 46 | 46 | Yes | 0 | NA | No | 50123.00 | 48522.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Sandi | KATRI CHHOCHPUR | 412568 | KATRI CHHOCHPUR | 776 | 776 | 100 | Har Gar Jal | Not Certified | 
| 2 | Hardoi | Sandi | CHANDRAMPUR PANSALA | 412569 | Chandrampur Sisala | 92 | 92 | 100 | Har Gar Jal | Not Certified | 
| 3 | Hardoi | Sandi | CHANDAU TIGAWAN | 412585 | CHANDAU BECHEY | 277 | 277 | 100 | Har Gar Jal | Not Certified | 
| 4 | Hardoi | Sandi | CHANDAU TIGAWAN | 412586 | CHANDAU BAKKHA | 54 | 54 | 100 | Har Gar Jal | Not Certified | 
| 5 | Hardoi | Sandi | CHANDAU TIGAWAN | 412587 | PURA ROHAN | 106 | 106 | 100 | Har Gar Jal | Not Certified | 
| 6 | Hardoi | Sandi | CHANDRAMPUR PANSALA | 677603 | CHANDRAMPUR PANSALA | 47 | 47 | 100 | Har Gar Jal | Not Certified |