Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Budaun | PNC-SPML-JV | 20068396 | Rafi Nagar & Lahra Asdullapur Water Supply Scheme | 391.81 | 77.65 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 30 | 30 | Yes | 0 | NA | No | 12379.00 | 12379.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Sahaswan | Rafi Nagar | 401470 | Rafi Nagar | 188 | 185 | 98 | Work In Progress | Not Certified | 
| 2 | Budaun | Sahaswan | Rafi Nagar | 401471 | Khirwara | 88 | 87 | 99 | Work In Progress | Not Certified | 
| 3 | Budaun | Sahaswan | Lahra Asdullapur | 401473 | Lahra Asdullapur | 287 | 287 | 100 | Har Gar Jal | Not Certified |