| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20068462 | KARAUNDI & KALYANPUR Village Village water supply scheme | 580.83 | 249.23 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 30 | 30 | Yes | 0 | NA | No | 42262.00 | 16960.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Machhlishahr | Karaudi | 469604 | Visunpur | 100 | 88 | 88 | Work In Progress | Not Certified |
| 2 | Jaunpur | Machhlishahr | Karaudi | 469605 | Barahata | 73 | 67 | 92 | Work In Progress | Not Certified |
| 3 | Jaunpur | Machhlishahr | Karaudi | 469606 | Karaudi | 227 | 214 | 94 | Work In Progress | Not Certified |
| 4 | Jaunpur | Machhlishahr | Karaudi | 469607 | Meerpur Ta. Karaudi | 91 | 78 | 86 | Work In Progress | Not Certified |
| 5 | Jaunpur | Machhlishahr | Kalyanpur | 469620 | Kalyanpur | 90 | 78 | 87 | Work In Progress | Not Certified |
| 6 | Jaunpur | Machhlishahr | Kalyanpur | 469621 | Sonhara | 83 | 75 | 90 | Work In Progress | Not Certified |