Scheme Details
DISTRICT
Jaunpur
AGENCY
AFCONS
SCHEME ID
20068468
SCHEME NAME
KARAUNDA & JAGARNTHPUR & NADAAN Village water supply scheme
ESTIMATED COST
458.60
EXPENDITURE
230.78
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
46611.00
Meter
Length Laid
0.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Machhlishahr | Nadan | 469535 | Nadan | 57 | 57 | 100% | Har Ghar Jal | Not Certified |
| 2 | Jaunpur | Machhlishahr | Nadan | 469537 | Addopur | 65 | 59 | 91% | Work In Progress | Not Certified |
| 3 | Jaunpur | Machhlishahr | Karaunda | 469546 | Karaunda | 179 | 166 | 93% | Work In Progress | Not Certified |
| 4 | Jaunpur | Machhlishahr | Jagarnathpur | 469547 | Jagarnathpur | 72 | 72 | 100% | Har Ghar Jal | Not Certified |
| 5 | Jaunpur | Machhlishahr | Jagarnathpur | 469548 | Chak English Chak Chain Singh | 38 | 30 | 79% | Work In Progress | Not Certified |
| 6 | Jaunpur | Machhlishahr | Jagarnathpur | 469549 | Hiqamuddinpur | 53 | 49 | 92% | Work In Progress | Not Certified |