Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Vindhya-GAJA (JV) | 20068470 | REVAI WSS | 234.16 | 150.75 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 16 | Yes | 0 | NA | No | 8784.00 | 8284.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Jalalpur | Revai | 438284 | Revai | 449 | 447 | 100 | Work In Progress | Not Certified |
| 2 | Ambedkar Nagar | Jalalpur | Revai | 438285 | Rampur Khurd | 22 | 22 | 100 | Har Gar Jal | Not Certified |
| 3 | Ambedkar Nagar | Jalalpur | Revai | 438286 | Vanganw | 46 | 46 | 100 | Har Gar Jal | Not Certified |