Scheme Details
DISTRICT Budaun
AGENCY PNC-SPML-JV
SCHEME ID 20068525
SCHEME NAME baksena & sainjani water supply scheme
ESTIMATED COST 509.03
EXPENDITURE 153.42
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 37
Procured 37 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 23978.00 Meter
Length Laid 21200.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Budaun Dataganj Sainjani 402352 Sainjani 508 505 99% Work In Progress Not Certified
2 Budaun Dataganj Baksena 402353 Baksena 741 741 100% Har Ghar Jal Not Certified
3 Budaun Dataganj Baksena 402354 Gadhiya Laksha 21 18 86% Work In Progress Not Certified
4 Budaun Dataganj Sainjani 660497 BHAGAUDA 62 58 94% Work In Progress Not Certified