Scheme Details
DISTRICT
Sitapur
AGENCY
NCC Ltd.
SCHEME ID
20068543
SCHEME NAME
Bisun Nagar & Sarai Yusuf Water Supply Scheme
ESTIMATED COST
378.98
EXPENDITURE
240.88
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
28
Procured
28
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16278.00
Meter
Length Laid
16153.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Khairabad | Bishun Nagar | 410569 | Bishun Nagar | 310 | 308 | 99% | Work In Progress | Not Certified |
| 2 | Sitapur | Khairabad | Sarai Yusuf | 410625 | Aam Khera | 125 | 114 | 91% | Work In Progress | Not Certified |
| 3 | Sitapur | Khairabad | Sarai Yusuf | 410627 | Sarai Yusuf | 166 | 154 | 93% | Work In Progress | Not Certified |