Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Sitapur
AGENCY NCC Ltd.
SCHEME ID 20068595
SCHEME NAME Sarosa & Udaipur Poorvi Water Supply SCheme
ESTIMATED COST 583.14
EXPENDITURE 317.33
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 42
Procured 42 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 21516.00 Meter
Length Laid 21516.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sitapur Gondlamau Sarosa 410146 Sarosa 568 566 100% Work In Progress Not Certified
2 Sitapur Gondlamau Udaipur Poorvi 410159 Udaipur Poorvi 449 449 100% Har Ghar Jal Not Certified