Scheme Details
DISTRICT
Budaun
AGENCY
PNC-SPML-JV
SCHEME ID
20068746
SCHEME NAME
Kohni Jafrabad & Bhagwanpur Water Supply Schme
ESTIMATED COST
313.85
EXPENDITURE
176.70
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10859.00
Meter
Length Laid
10859.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Samrer | Bhagawanpur | 402254 | Bhagawanpur | 219 | 213 | 97% | Work In Progress | Not Certified |
| 2 | Budaun | Samrer | Kohni Jafrabad | 402255 | Fatehpur | 61 | 60 | 98% | Work In Progress | Not Certified |
| 3 | Budaun | Samrer | Kohni Jafrabad | 402256 | Kohni Jafrabad | 192 | 188 | 98% | Work In Progress | Not Certified |