Scheme Details
DISTRICT
Ambedkar Nagar
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20068847
SCHEME NAME
MANGOLPUR WSS
ESTIMATED COST
317.60
EXPENDITURE
215.62
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14996.00
Meter
Length Laid
14996.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Ramnagar | Rampur Saray | 437921 | Rampur Saray | 104 | 104 | 100% | Har Ghar Jal | Not Certified |
| 2 | Ambedkar Nagar | Ramnagar | Mangolpur | 437922 | Gadanpur | 82 | 82 | 100% | Har Ghar Jal | Not Certified |
| 3 | Ambedkar Nagar | Ramnagar | Mangolpur | 437923 | Mangolpur | 77 | 75 | 97% | Work In Progress | Not Certified |
| 4 | Ambedkar Nagar | Ramnagar | Rampur Saray | 437924 | Saraya Neel Kanth | 48 | 46 | 96% | Work In Progress | Not Certified |
| 5 | Ambedkar Nagar | Ramnagar | Mangolpur | 437925 | Addopur | 3 | 1 | 33% | Work In Progress | Not Certified |
| 6 | Ambedkar Nagar | Ramnagar | Rampur Saray | 437926 | Hajanpur | 9 | 6 | 67% | Work In Progress | Not Certified |