Scheme Details
DISTRICT
Maharajganj
AGENCY
Rithwik-Koya (JV)
SCHEME ID
20068849
SCHEME NAME
BARHYA MUSTAKIL WATER SUPPLY SCHEME
ESTIMATED COST
425.51
EXPENDITURE
92.54
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
10
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14885.00
Meter
Length Laid
10001.00
Meter
Scheme Assigned Villages
8 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Maharajganj | Nichlaul | BHADIYA FAST | 453730 | BHADIYA FAST | 766 | 765 | 100% | Work In Progress | Not Certified |
| 2 | Maharajganj | Nichlaul | BHADIYA FAST | 652466 | BANKASIYA | 54 | 53 | 98% | Work In Progress | Not Certified |
| 3 | Maharajganj | Nichlaul | BHADIYA FAST | 652467 | LAXMIPUR | 61 | 61 | 100% | Har Ghar Jal | Not Certified |
| 4 | Maharajganj | Nichlaul | KALNAHIN KHURD | 652473 | Kalnahin Kala | 87 | 1 | 1% | Work In Progress | Not Certified |
| 5 | Maharajganj | Nichlaul | KALNAHIN KHURD | 652474 | Aurahiya | 257 | 5 | 2% | Work In Progress | Not Certified |
| 6 | Maharajganj | Nichlaul | Shikarpur | 652480 | Banspati | 100 | 1 | 1% | Work In Progress | Not Certified |
| 7 | Maharajganj | Nichlaul | Shikarpur | 652481 | Vakulhiya | 30 | 1 | 3% | Work In Progress | Not Certified |
| 8 | Maharajganj | Nichlaul | KALNAHIN KHURD | 658450 | BAISAHIYA | 1 | 1 | 100% | Har Ghar Jal | Not Certified |