Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Megha | 20068871 | Sukhipur Water Supply Scheme | 395.15 | 173.00 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 31 | 31 | Yes | 0 | NA | No | 20717.00 | 10620.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Puredalai | Sukhipur | 435695 | Sukhipur | 500 | 497 | 99 | Work In Progress | Not Certified |
| 2 | Barabanki | Puredalai | Kurha | 435696 | Kurha Sukhipur | 266 | 263 | 99 | Work In Progress | Not Certified |