Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Barabanki
AGENCY Megha
SCHEME ID 20068911
SCHEME NAME Uchita Water Supply Scheme
ESTIMATED COST 237.29
EXPENDITURE 107.63
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 8432.00 Meter
Length Laid 7081.00 Meter

Scheme Assigned Villages

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Barabanki Siddhaur Uchita 435972 Uchita 208 202 97% Work In Progress Not Certified
2 Barabanki Siddhaur Uchita 435973 Khwajapur 113 109 96% Work In Progress Not Certified
3 Barabanki Siddhaur Uchita 435974 Husainpur 134 131 98% Work In Progress Not Certified