Scheme Details
DISTRICT
Jaunpur
AGENCY
AFCONS
SCHEME ID
20068918
SCHEME NAME
SUKARANA KALAN VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST
290.12
EXPENDITURE
165.76
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
20482.00
Meter
Length Laid
18457.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Suithkala | Sukarana Kalan | 468188 | Sukarana Khurd | 79 | 72 | 91% | Work In Progress | Not Certified |
| 2 | Jaunpur | Suithkala | Sukarana Kalan | 468189 | Sukarana Kalan | 194 | 194 | 100% | Har Ghar Jal | Not Certified |
| 3 | Jaunpur | Suithkala | Sukarana Kalan | 468190 | Chiliram | 156 | 130 | 83% | Work In Progress | Not Certified |