Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Megha | 20068991 | Saidanpur & Sarai Belhari Water Supply Scheme | 394.24 | 124.18 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 18860.00 | 18120.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Siddhaur | Saidan Pur | 435907 | Saidan Pur | 390 | 387 | 99 | Work In Progress | Not Certified | 
| 2 | Barabanki | Siddhaur | Saidan Pur | 435908 | Khwaja Pur | 134 | 132 | 99 | Work In Progress | Not Certified | 
| 3 | Barabanki | Siddhaur | Sarai Belahri | 435909 | Sarai Belahri | 205 | 205 | 100 | Har Gar Jal | Not Certified | 
| 4 | Barabanki | Siddhaur | Sarai Belahri | 435910 | Basiya Mau | 51 | 47 | 92 | Work In Progress | Not Certified | 
| 5 | Barabanki | Siddhaur | Sarai Belahri | 435911 | Bahadur Pur | 109 | 106 | 97 | Work In Progress | Not Certified |